What’s Included in a Limestone Milling Plant Quote?

Artículo de noticias 680

When two limestone milling plant quotes both list a “grinding system,” bring them to the same scope of work before comparing total prices. If the project calls for connecting the system to an existing feed silo, delivering slurry to the storage tank inlet, and completing on-site commissioning, check both quotes against those requirements. For any required work outside a quote, ask the equipment supplier to price it separately or add the cost of arranging it yourself.

The connections between pieces of equipment can make a difference to the comparison. Even if you already have a feed silo and a slurry storage tank, you may still need to buy the chute from the silo outlet to the feeder and the piping from the grinding system outlet to the tank inlet. List those items in a scope matrix so you can see exactly where each supplier’s responsibility ends.

Mark the Supply Boundaries on the Same Drawing

For the wet limestone grinding system at India’s NTPC Dadri power plant, part of a flue gas desulfurization project, buyer BHEL kept the feed silo and slurry storage tank within its own scope. It required bidders to provide the chute from the silo outlet to the feeder and extend the slurry piping to the tank inlet. That division of work was specific to Dadri. The practice you can apply to another project is to define each party’s scope at a specific connection point.

Ask both suppliers to mark where their scope begins and ends on the same process flow diagram. Then check which equipment and connecting components are listed in each quote. If both say “up to the slurry storage tank,” ask them to identify the tank inlet on the drawing and confirm whether the price includes the piping, valves, and supports along that run. If one supplier stops at the grinding system outlet, list the remaining work separately and have the supplier or the site contractor price it.

Limestone Milling Plant Scope Of Supply Diagram Showing Feed Silo, Grinding System, Slurry Piping, Storage Tank And Equipment Handover Points

If you plan to reuse a silo or tank, ask the suppliers to confirm the connection points. If the new system can connect directly, compare the quotes using the connection points you’ve agreed with each supplier. If modifications are needed, identify the work and who will do it, then add the cost to the relevant option.

Separate Site Installation From Technical Supervision

If a quote says “installation and commissioning included,” ask who provides the installation crew and lifting equipment, who installs and wires the equipment on site, and who operates it during commissioning. The Dadri tender included supervision of installation and commissioning in the supplier’s scope. If a supplier quotes supervision, that covers technical oversight. Check the quote separately for the installation crew and equipment.

If you already have a site contractor, give them the connection drawing and equipment list so they can price the work. Then confirm when the equipment supplier will be on site and what work they will supervise. If no contractor has been assigned, ask the equipment supplier to price the installation separately or get a quote from a third party. Either arrangement can be included in the comparison once you know who will do the work and what it will cost.

Compare Both Quotes Against the Same Handover Requirements

Hypothetical example. The buyer already has a feed silo and a slurry storage tank. The required scope includes the connections from the silo outlet to the tank inlet, with the system installed and commissioned for handover. Quote A has the lower total. Here’s how the two quotes break down.

ItemQuote AQuote BHow to Compare
Chute from the feed silo outlet to the feederExcludedIncludedAdd a separate price for the chute to Quote A.
Piping from the grinding system to the tank inletSupply ends at the grinding system outletSupply extends to the tank inlet, with no mention of supportsGet a price for the piping, valves, and supports beyond the outlet for Quote A. Ask Supplier B to confirm in writing whether supports are included.
On-site installation and commissioningIncludes installation supervision and on-site commissioning. The installation crew and lifting are priced separately.Includes installation work and commissioning. The buyer arranges lifting.Add the cost of the crew and lifting to Quote A. Add the cost of lifting to Quote B. Check whether the installation priced for each option covers the connections listed above.

In this example, Quote A needs to include the cost of the chute, the outlet piping, and the installation work. For Quote B, the buyer still needs to confirm whether supports cost extra. Both options require lifting arrangements. Add any missing work to the relevant quote once you know who will do it and what it will cost. If a required item still has no assigned party or price, mark it as open and hold off on ranking the quotes by total price.

Send both suppliers the process flow diagram and the scope matrix. Ask them to mark each item as included, priced separately, or excluded, show the connection points on the drawing, and provide optional prices for any required work they’ve excluded. Once they reply, have your site contractor price the work assigned to you, then record the agreed responsibilities and prices in a single attachment to the purchase order.